Which side of the Forge River sewer map does a house in Mastic, Mastic Beach or Shirley sit on? The answer is already part of the price, whether or not anyone has negotiated it.
Suffolk County's Forge River Watershed Sewer Project splits the peninsula into groups. Some are already being connected, one is in design and one is still years away. Each group carries its own costs, paperwork and timing. On two similar houses a few blocks apart, sewer status can be the biggest difference between them, and it doesn't appear in a listing photo.
Quarterly sewer charges
The project site describes a quarterly debt service charge for Phases I and II, covering project design costs that grants didn't pay for. It also describes a user fee for connected properties, covering the cost of running the district. The site says some owners may get bills before their connection is made; whether a charge applies to a particular property is a question for the county.
Sewer billing also changed this year. As of January 1, 2026, all Suffolk County sewer districts were consolidated into the Suffolk County Wastewater Management District. The county's sewer billing page says sewer charges no longer appear on the property tax bill. It describes separate billing by the new district for connected properties; the rate or billing method may have changed with the consolidation. For a buyer working out monthly costs, it's worth asking about sewer bills.
Access agreements and connection costs
In January 2024, the county mailed access agreements to every property owner in Phases I and II. The agreements cover county contractors' access to install sewer equipment. The project site describes the Forge River Sewer District as responsible for grinder pump maintenance, repair and replacement.
The Forge River project site discusses potential connection costs for owners who didn't sign before grinder pump work began or who opted out. It estimates $20,000 for installing the grinder pump and abandoning the old cesspool or septic system.
The project site doesn't say how that cost is handled when a house changes hands; whether it applies to an address or transfers on sale is a question for the county and your attorney before closing. A buyer who assumes "it's in the sewer district, so it's handled" may be assuming wrong. For any Phase I or II address, the access agreement history is one of the first things to ask about.
Three phases on one peninsula
The groups follow geography, and county documents describe them by named roads and waterways. The district boundaries were drawn to take in properties within a two-year groundwater travel time of the Forge River. That's why the first phases sit closest to the river.
| Group | Where, per county documents | Status as of November 2026 | Project details |
|---|---|---|---|
| Phases I and II | The Montauk Highway corridor between William Floyd Parkway and the Forge River, plus residential parcels between Sunrise Highway and Poospatuck Creek | Treatment plant complete and taking flow; home connections described as nearing completion | Quarterly debt service and user charges; project site discusses possible connection costs |
| Phase III | North: Poospatuck Creek and Meadowmere Avenue. West: Mastic Road. East: the Forge River. South: the William Floyd Estate, Washington Avenue and Wavecrest Drive | Design funded and underway; field visits this fall | Cesspool or septic system still in use; county survey team visits each home |
| Phase IV | About 6,500 mostly residential parcels south of Mastic Road, Parkwood Drive and Wavecrest Drive, down to Narrow Bay and Bellport Bay | Planned; start depends on design funding | Cesspool or septic system for the foreseeable future |
The treatment plant at Calabro Airport is finished and now accepts flow from Phase I and II homes. Posillico-Bove and Grace Industries hold the five grinder pump contracts. The project's posted schedule has the last of them, Contract 9, ending in Fall 2026. Those dates are labeled as anticipated and could change, so a house inside the Phase I and II lines may or may not be connected yet. The project site has an address search for checking whether a property is inside the Phase I and II boundary.
Phase III is knocking on doors this fall
This is where the timeline shapes a purchase most. The Phase III page says the phase covers about 1,500 more properties in the Mastic area, and its design has been approved. Suffolk County Department of Public Works has hired the consultants Gannett Fleming and SAM-NY Geospatial Inc. to survey the area. Starting this fall, team members are visiting every home in the Phase III area. They locate water and electrical lines, find the existing cesspool or septic system, and take exterior photos. Before a visit, owners get a door hanger with the expected week. They book an appointment and can fill out a property questionnaire online or on paper.
Construction runs on a longer schedule. In the county's adopted 2026–2028 capital program, Phase III has $8 million already set aside for planning and design. The $201.6 million construction line is placed in the "subsequent years" column, after 2028. The county's proposed 2027–2029 capital program, dated April 2026, lists $36 million for Phase III to "design and construct" the extension within the same boundaries. The county's July 2025 wastewater implementation plan estimated Phase III would be finished in July 2030. The project FAQ says the county has secured funding for Phase III design and survey work and is still looking for construction funding.
For a Phase III buyer, the house will likely run on its current cesspool or septic system for years. Its condition matters now, and the sewer is a planned future change. A seller there should expect buyers to ask about the field visit and whether the questionnaire was sent in.
Phase IV, which covers most of the bay side of Mastic Beach, is further out still. The adopted capital program schedules $40 million for 2028 and $600 million for subsequent years. The implementation plan gives a start date of "11/1/2027 if design funds are secured" and a December 2032 completion target.
What a connection changes inside the house
A connected house in Phases I and II has equipment a buyer should know about at the inspection. The connection includes a grinder pump unit on the property, a gravity pipe from the house's waste line to the pump, and an electrical control panel on the outside of the home.
The grinder pump runs on the home's electricity. The project FAQ says that during a power outage, toilets, sinks and limited showers still work, but dishwashers and washing machines don't. The tank is sized to hold water use during an outage. For a long outage, the alarm panel has a generator receptacle so the pump can run and drain the tank from time to time. A buyer who plans to use a generator should know about that receptacle before the first storm.
When the plant opened in March 2025, Newsday reported that the system was expected to connect about 1,900 homes in a district running from William Floyd Parkway to the Forge River, south of Sunrise Highway. At the opening, Suffolk Legislator James Mazzarella said Montauk Highway businesses would benefit, according to Messenger Papers. The county's capital program describes sewering as "essential to economic growth and affordable/workforce housing" on the peninsula.
Questions to settle for one specific address
Before an offer, or before you set a list price, these questions sort a house into its group and show what comes with it:
- Is the property inside the Phase I and II district? Check the address on the project site's map search.
- If it's inside, is it connected? The county takes connection-status questions at [email protected].
- Did the owner sign and return the access agreement? The project site discusses access agreements and potential connection costs.
- What sewer billing information is available? Ask about the most recent Wastewater Management District bill, since sewer charges are no longer on the tax bill. Billing questions go to (631) 852-4060 or [email protected]. Phase I and II billing questions can also go to [email protected].
- If it's in Phase III, has the field visit happened? Ask whether the door hanger arrived and the questionnaire went in.
- If it's in Phase III or Phase IV, what condition is the cesspool or septic system in? That system is the one the house will rely on for now.
A few questions I hear often
Is this the same as the county's septic grant program? No. The project FAQ says the sewer project and the Septic Improvement Program, which gives grants for on-site systems, are two separate county initiatives.
Can the district boundary be extended to include a house? The boundaries were set to take in properties within the two-year groundwater travel time to the Forge River, and those properties were the priority for the first phases.
This post is general information, not legal, tax or financial advice. Please confirm how these charges and obligations apply to your property with the county, your attorney or the right professional.
If you own a home on the Mastic peninsula and want to know how its sewer status affects what it's worth today, start with a free home valuation. If you're a buyer comparing addresses, let's connect. I'm glad to go through these questions with you in English or Spanish before you make an offer. Sophia Walker REALTOR®